Project Description

Brasimba Brewery Project- Beni- North Eastern Congo

Principal:
Castle Brewery, Antwerp- Belgium
Client:

Bollore Africa Logistics Kenya Ltd
Starting Date:
July 2012
Completion Date:
October 2012
Place of Delivery:
Beni- North Eastern Congo
Mileage from Mombasa:
1,645 Kilometres

Details:

Inland Transport of Brewery Tanks and Brewery installation equipment/ machinery.

  • Heaviest piece transported: 45mt all Terrain Crane.
  • Widest pieces transported: 16 meters in length and 6.5 meters in diameter (Brewery fermentation tank).
  • Total CBM handled: 6,000CBM.
  • Total Containers handled: 175 TEUs.